Dosing Pump

Pick one or more effluent pumps that can dose the absorption area or the treatment filter.

When you see this page

The page has two versions:

Version List heading
To Discharge Pump Selection for Discharge Dosing
To Filter Pump Selection for Filter Dosing

To Discharge follows Discharge Pump Plumbing on any pumped absorption area. To Filter follows Filter Pump Plumbing on Puraflo, Buried Sand Filter and Recirculating Sand Filter (SFTF) designs.

The list

  • Pumps are grouped by manufacturer. Pumps that don’t qualify are greyed out and can’t be selected.
  • When dosing from an Ecoflo unit, the list shows only pumps that fit the Ecoflo.
  • You can select several pumps. Each selected pump is listed in the report as an acceptable option.

Which pumps qualify

To Discharge: a pump qualifies when its head at the design flow rate is greater than the total head plus the persona’s Minimum head surplus. The total head comes from the elevation, the delivery line and the fittings.

To Filter: each pump is rated for flow suitability by the filter’s rules. If any pump rates Okay, only those qualify. Otherwise pumps rated Marginally High qualify too.

Pre-selection

On a first visit, one pump is pre-selected in each manufacturer group:

  • To Discharge: the lowest-horsepower pump that qualifies.
  • To Filter: the pump with the lowest flow.

Your selection is kept on a later visit unless the flow rate, total head, filter count, filter elevation or persona has changed.

Pump curves

The summary panel draws a curve for each selected pump. The pump’s head-versus-flow curve is in blue, and the system demand point is in red.

Messages

  • Select at least one pump!
  • To Discharge, when no pump gives enough head, the message names the closest pump, for example: No pump in the list gives enough head. The closest is Zoeller 295 2 HP: at 161.2 gpm it gives 24.9 ft of head, and this design needs 33.7 ft (32.7 ft total head plus a 1.0 ft margin). Of the total head, 19.7 ft is friction in the 2.0 in. delivery line: choose a larger delivery line on Discharge Pump Plumbing. The last sentence appears only when Discharge Pump Plumbing lists a larger line. Otherwise try fewer fittings or a shorter run, or lower the persona’s Minimum head surplus.
  • To Discharge, when the flow is past the end of every pump’s curve: No pump in the list delivers 161.2 gpm: this design’s flow is past the end of every pump’s curve.
  • To Filter: No pumps available! No pump in the database meets the requirement.

With the Norweco Singulair 960-500 two-tank system (chosen on Tank Selection: Aerobic), the pump chamber is the dosing tank, so the page also checks that it can take the dose. The tank name and the numbers come from the catalogue:

  • The Singulair 960-500 w/ 640 gal pump chamber can dose at most 320 gal; this design needs more. Go back to Tank Selection and choose another Singulair tank. The dose is over the chamber’s 320 gal limit.
  • The Singulair 960-500 w/ 640 gal pump chamber is too small for this design’s dose. Go back to Tank Selection and choose another Singulair tank. The minimum dosing tank is over 640 gal (for example, where the permitting agency requires a 1000 gal dosing tank), or the pump-on level would be above the chamber’s 51 in liquid depth.

When no catalog pump fits

When no pump in the catalog qualifies, a Designer specified pump card appears above the pump list, on To Discharge or To Filter. It reads No pump in our catalog meets this design. and offers two choices:

  • I’ll use a pump I’ve chosen. Enter the pump’s Make, Model and Rated flow (gpm at ft of head). Under the fields, the card shows what the pump must deliver, for example Required: at least 35.0 gpm at 405.3 ft of head. On To Discharge that head includes your persona’s Minimum head surplus. On a Puraflo filter, the flow must also be no more than 20 gpm per filter module.
  • Continue without specifying a pump. The fields are greyed out. When you click Next, Sewers asks You must attach specifications, including pump curve, for a suitable pump to the design. Accept goes on, and Cancel stays on the page.

Messages on Next:

  • Enter the pump’s make, model, rated flow and head. A field is blank.
  • The pump you entered does not meet flow/head requirements. The pump’s flow or head is below the requirement, or, on a Puraflo filter, its flow is over 20 gpm per module.
  • If you choose neither, Next shows the no-pump message described above.

If a catalog pump qualifies again later (say, after you change the delivery line), the card goes away and the page works as usual. Picking a catalog pump replaces your earlier choice.

In the report

  • The equipment list keeps the line Effluent pump delivering at least … gpm at … ftH2O. It is followed by your pump, for example Pump: Acme P100, rated 35 gpm at 405.3 ft of head. See attached pump specifications., or, if you continued without one, See attached pump specifications. On To Discharge this line leaves out the Minimum head surplus, so it can be 1 ft or so below the card’s figure.
  • There’s no pump curve. The curves section says Performance curve: see attached pump specifications.
  • For a Puraflo or Recirculating Sand Filter (SFTF), the dosing section says Dose duration: see attached pump specifications.
  • The wiring section links to the wire-size chart at bjsoftware.com/support/pump-wire-size. When the design’s other pump is from the catalog (a catalog discharge pump after a Puraflo filter, say), the report still prints the wire chart and adds the link after it. Otherwise the link replaces the chart.

Attach the pump’s specifications, including its curve, to the permit application.

Tips

  • A higher Minimum head surplus in your persona rules out more pumps, but leaves more margin for field error.

Discharge Pump Plumbing, Filter Pump Plumbing, Tank Selection, Persona.